Function description of charging pile assembly production line

Leave a message

Function description of production line plan

There are two production lines, which are used for JP cabinets and charging piles in-line assembly production and online testing.

The production line adopts the power roller conveyor method, and the products are placed on pallets for transportation. The tray can quickly fix a variety of products.

The products flow from the west to the east, and the finished products are offline from the east.

The empty shell of the product is hoisted by KBK and gantry crane respectively.

The empty pallets are automatically picked up by the palletizer and placed on the transfer car next to the line. After a certain amount is stacked, the pallets are manually pushed back to the end of the line and lifted on the line by KBK.


The production line is composed of Nuogan's 1.8m and 2.4m standard conveying sections. Each standard section is equipped with an independent drive system, which can be controlled separately. Each standard section can be used as an assembly station to place a product.


way to control:


During assembly operation, after the product is transported to the current standard section, the stopper automatically blocks the product and the tray, and the roller stops automatically;


When the assembly is completed and it needs to be transported to the next station, the sensor of the next station will automatically determine whether the next station is empty. If it is empty, the previous station will be effective when the conveyor button is pressed. The rollers of the two front and rear stations will start to roll at the same time, and the product will be automatically transported from the previous station to the next station. If it is not empty, pressing the transport button at the previous station is invalid, and the rollers at the front and rear stations do not move.